From the Corp:

CLASSIFICATION: UNCLASSIFIED

We are looking at beginning spillway releases at Table Rock tomorrow.   The purpose of the spill will be to supplement hydropower releases under normal flood control operations.   We still have 1 unit down.   We are not sure of the timing or amount, but it will likely be the 5,000 - 10,000 range sometime tomorrow morning.  I will provide more information as I receive it tomorrow.  

Rodney Raley
Deputy Operations Project Manager
US Army Corps of Engineers
Table Rock Project Office  
4600 State Highway 165
Branson, Missouri  65616
(501) 340-1932

Share this post


Link to post
Share on other sites

Sorry, this is probably a stupid question, but what does this mean for the lake level on taneycomo?  I've never heard clear up to the dam. I always stop when I get to fall creek. Would the water be high enough to easily boat to the dam or would I still have to avoid obstacles and shallow water?

Thanks for any advice!

Share this post


Link to post
Share on other sites

After reading the "how to boat to the dam" post, it looks like you can run up the middle of the lake at 705.  So it shouldn't be a problem to run up to the dam even if they just continue to run 3 units, correct? Then if they open the gates it will be plenty deep pretty much everywhere?

Do you guys have any recommendations for fishing that kind of water? Jetkbaits? Do you think there will be any shad?

 

Thanks!

Share this post


Link to post
Share on other sites
3 minutes ago, netboy said:

You should have plenty of water to boat up to the dam.

Thanks!

I've always wanted to see the good gates open, but never timed it right. Maybe it'll happen this time.

Share this post


Link to post
Share on other sites

From the Corps

Please open gates 3, 5, 7, 8, and 9 to one foot (1') each at 0700 in the morning.  At 0800 please open the remaining gates (1, 2, 4, 6, and 10)  to one foot (1') each.  When the openings are complete we should have all 10 gates opened to one foot (1') each.  The total spillway release will be 10,500 cfs.  Combined with three hydropower units, the total release through the dam will be 20,000 cfs.  Please let me know when the gate openings are complete in the morning.

Share this post


Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.


×
×
  • Create New...

Important Information

By using this site, you agree to our Terms of Use.